Red Post Hill
Construction has begun to make the area a more accessible and safe space for all.
Construction for Red Post Hill began on 24 February 2025, and we aim to finish by mid-May. A works notification letter was sent to inform residents and stakeholders of the upcoming works.
If you have any issues regarding site works, phone 01732 600700 or email southwarkenquiries@fmconway.co.uk.
The main improvements are aligned with our Streets for People strategy and include:
- footway widening providing a more inclusive and accessible space
- pedestrian crossings and countdown timer for pedestrian priority
- measures to enhance safety and visibility for cyclists (advanced stop line)
- carriageway resurfacing creating smoother journeys for cyclists and vehicles
The works will be carried out in 7 phases.
Phase 1: 24/02/25 – 26/02/25
Corner of Red Post Hill & East Dulwich Grove - Remove Traffic Islands, Decommission Traffic Signal System
Phase 2: 27/02/2025 - 08/03/2025
Corner of Dulwich Village & Village Way - Remove Traffic Islands, Construct Kerb & Footway to design, Install new Traffic Signal Infrastructure
Phase 3: 10/03/2025 - 18/03/2025
Corner of Village Way & Red Post Hill - Construct kerb and footway to design and install new traffic signal infrastructure
Phase 4: 19/03/2025 - 26/03/2025
Corner of Red Post Hill & East Dulwich Grove - Construct kerb and footway to design and install new traffic signal infrastructure
Phase 5: 27/03/2525 - 05/04/2025
Corner of East Dulwich Grove & Dulwich Village - Construct kerb and footway to design and install new traffic signal infrastructure
Phase 6: 07/04/2025 - 25/04/2025
Scope of the junction - Installation of modernised traffic signal apparatus
Phase 7: 15/05/2025 - 17/05/2025
Carriageway resurfacing
Impact of works
Due to the temporary traffic lights, there may be some delays at the junction while works are ongoing. However, access will be maintained at all times for all road users. Temporary pedestrian crossings will be maintained at all arms of the junction.
Background
We have been working with the community to improve the Red Post Hill junction. This is following a decision made in March 2023 to make the Dulwich Village Junction re-design and Red Post Hill Junction improvements permanent.
View illustrations of our proposal at Red Post Hill.
View the full decision report.